The Ministry of Water, Agriculture and Environment, through the Directorate General of Rural Development and Forestry, develops different jobs for the consolidation of the hillsides of public utility in the municipality of Blanca, Ulea.
The Directorate-General carries out the management of the areas included in the Catalogue of Public Utility Woodland, where in some of them, as is the case of White and Ulea, the risk of landslides can be high.
Specifically, the Ministry has already begun the second phase of fall protection Blanca, amounting to 182,828 euros.
In addition, also it plans to undertake short time in the third phase of consolidation of slopes in the mountain of public utility 41 'Navela, The Solan, the Muela y Montero' in this municipality, budgeted at 795,437 euros.
The work of the first phase of fall protection Blanca ended last February and had a total cost of 211,173 euros.
Regarding the municipality of Ulea, DG working on the project to stabilize the stones that have fallen into the hillside.
The stretch of barrier that has been affected and will be increased by another 50 meters barrier in its western part was also repaired.
The total cost of the actions will be about 30,000 euros.
The Directorate General for Rural Development and Forestry has noted the success of the proposed consolidation of the slope on Mount Catalog No. 136 of Public Utility (CUP) called La Solana, Las Lomas, The Navela and La Serrata of Ulea.
Last September saw the release of a block of 20 cubic meters in the western part of the cut, but the containment barrier prevented the stones cause damage to neighboring houses.
Source: CARM